Product Breakdown Structure (PBS) & Work Breakdown Structure (WBS)

Breakdown structures are deliverable-oriented decompositions of a product or set of activities into smaller, logically structured components.

Breakdown structures can be organized by:

  • product
  • activity
  • or a combination of both

Product Breakdown Structure (PBS)

The Product Breakdown Structure (PBS) is a hierarchical structure of products that a project will create or the outcomes it will deliver.

In product-based project management methods such as PRINCE2, planning starts with the PBS.
Other methodologies sometimes refer to product-based Work Breakdown Structures (WBS) when they are effectively describing a PBS.


Work Breakdown Structure (WBS)

The Work Breakdown Structure (WBS) provides a hierarchical structure of project activities that organizes the team’s work into manageable sections.

The output of these activities are the products structured in the PBS.

➡️ WBS training


PBS in the project schedule

Project schedules should be structured based on the Product Breakdown Structure.
This approach provides a clear overview and makes it easy to track progress and remaining work per product.

In the example below, the PBS is integrated directly into the Gantt chart, meaning:

  • the PBS becomes part of the project schedule
  • no separate PBS maintenance is required

For most projects, this approach is the most efficient.


Example: PBS translated into a project schedule

We took a random PBS from the internet and translated it into a product-based project schedule.

Product Breakdown Structure example

(Click to enlarge)


PBS project plan – step 1
Elite-Sport Performance Management

Sports Coaching

Discover a complete approach to sports coaching, with programs and insights for cycling, performance training, and talent development. From structured cycling workouts and zone-based training to AI-supported coaching platforms, we help athletes at every level train smarter, improve performance, and achieve their goals. Join our community of riders and benefit from expert guidance, practical tools, and evidence-based strategies to maximize results.

Read more

Companies

Dutch Disruption

At Dutch Disruptions, we create innovative apps and trading tools that make information and insights accessible to everyone.

Our apps — from Immoinfo and GIGAgoedkoopste to DJtracks, radarITALIA, Corona-Warn-App BLOCKER, and jouwNIEUWS — deliver real-time data, personalized tools, and enhanced privacy, all available on the App Store and Google Play.

Dutch Disruption